BIM for facility management: what are COBie and digital handover?
Most of a building's cost is in operation
Most of the money spent over a building's life is spent after construction, during operation and maintenance. Yet in many buildings handover documents are drawings and catalogues scattered across folders. Finding a valve, an air handling unit's warranty period or the circuits fed by a switchboard can take hours. BIM-based digital handover collects this information in one searchable structure.
From project model to asset model
In the ISO 19650 approach, the model created during design and construction is the project information model (PIM), and the model handed over to operations is the asset information model (AIM). ISO 19650-3 covers information management during operation. For a smooth transition, the client's information requirements and formats must be defined at the very start, in the BIM Execution Plan.
What is COBie?
COBie (Construction Operations Building information exchange) is an international data format for passing building and equipment information to operations. It is usually delivered as a spreadsheet and can be imported directly into facility management software.
| COBie sheet | Content | Example |
|---|---|---|
| Facility / Floor / Space | Building, floors and rooms | Level 3 — Room 3.14 Meeting Room |
| Type | Equipment types and shared data | AHU type, manufacturer, warranty period |
| Component | Individual equipment | AHU-03, serial number, installation date |
| System | Systems equipment belongs to | Chilled water system, emergency lighting |
| Job / Spare | Maintenance tasks and spare parts | Filter replacement every 3 months |
What must be done in the model?
- Parameters needed for operation are defined in Revit families from the start.
- Room, system and equipment naming follows one standard.
- Data of the products actually installed is entered during construction, and the model is updated to as-built.
- Data completeness and accuracy are checked before handover.
Benefits for operations
An operations team with a digital handover sees equipment locations in the model, generates maintenance schedules automatically, tracks warranties and quickly identifies areas affected by a fault. Refurbishment projects can also start directly from an up-to-date model without re-surveying.
See our Services page for details of Sönmez Mühendislik's services, and our Blog for more technical articles.
Frequently asked questions
Click a question to see the answer.
BasicsIs COBie mandatory?

TimingWhen should digital handover be planned?
ModelCan the design model be handed straight to operations?
SoftwareWhich FM software does it work with?

ExistingCan it be done for existing buildings?
BenefitWhat is the biggest benefit?