How is an electric vehicle charging infrastructure project prepared?

Short answer: A charging project starts by defining how many vehicles will charge and at what power (AC 7–22 kW or DC fast charging). Then transformer and switchboard capacity is checked, a load management system is designed to share power, suitable cabling, residual current protection and earthing are specified for each point, and conduit and switchboard reserve is left for future expansion.

AC or DC?

In residential, office and shopping mall car parks vehicles stay parked for long periods, so AC chargers (7.4 kW single-phase, 11–22 kW three-phase) are usually enough. Fuel stations, fleet depots and motorway facilities with short stops need DC fast charging (50 kW and above). This choice directly sets transformer size, switchboard design and cable sizes.

UseTypical chargerPower rangeDesign impact
Residential car parkAC wall box7.4–11 kWSupply from flat meters or common board; load management essential
Office / mallAC pedestal11–22 kWFloor boards, metering and billing infrastructure
Fleet / logisticsAC + DC22–150 kWA new transformer or capacity upgrade may be needed
Roadside facilityDC fast charging50–350 kWMV connection, harmonic and power factor studies

Capacity check and load management

Fifty cars drawing 11 kW at once add 550 kW of new load. Most existing buildings lack that transformer reserve. So the existing load profile is reviewed first, then dynamic load management is designed: the system adjusts the power delivered to chargers according to the building's real-time demand, allowing many more charging points without replacing the transformer.

NeedVehicles, charger typeCapacityTransformer, board reserveConceptLoad management, meteringDesignCables, protection, routesCommissioningTests, software setup
Figure 1 — Steps of a charging infrastructure project.

Protection, cabling and earthing

  • Each charging point has its own circuit and overcurrent protection.
  • Against DC leakage from the vehicle, Type B residual current devices or chargers with DC leakage detection are used.
  • On long car-park routes, cable sizes are verified by voltage drop calculation.
  • Earthing and equipotential bonding are designed together with the building's overall earthing system.

Fire safety in enclosed car parks

The location of charging areas in enclosed car parks should be assessed together with smoke extraction, sprinkler coverage and fire brigade access. An emergency stop that cuts power to all chargers and integration with the fire alarm system are recommended.

Leaving reserve for the future

EV numbers grow every year. Even if only a few chargers are installed today, providing conduit and tray routes to every parking space and spare switchboard capacity avoids costly breaking and re-cabling later. Mandatory charger ratios in the current Turkish car park regulation should also be checked during design.

See our Services page for details of Sönmez Mühendislik's services, and our Blog for more technical articles.

Frequently asked questions

Click a question to see the answer.

Akfen Merter Office Building — 35,000 m²
BasicsCan chargers be added to an existing building?
Yes. Transformer and switchboard reserve is reviewed first; if it is limited, load management keeps the chargers within the existing capacity.
CapacityWhy is load management needed?
All vehicles rarely charge at full power at the same time. Load management shares power according to real demand and greatly reduces the need for a larger transformer.
ProtectionWhich residual current protection is used for chargers?
Because of possible DC leakage from the vehicle, a Type B RCD or a charger with DC leakage detection is preferred.
Akfen Merter Office Building — 35,000 m²
SpeedWhat is the difference between AC and DC charging?
With AC, the vehicle's on-board charger converts the current, usually limited to 22 kW. With DC, conversion happens in the station and much higher power is possible.
MeteringHow is charging cost shared in a residential car park?
Chargers with per-unit metering and user identification can report consumption per flat.
SafetyIs charging safe in an enclosed car park?
With proper design, yes. Protection, emergency stop, fire alarm integration and smoke extraction must be designed together.