Engineering data centers: uptime starts with design

Short answer: A data center project starts by defining the target Tier level. That target decides how many redundant paths (N, N+1, 2N) the power, cooling and distribution systems need, and therefore the budget. Running structural, electrical and mechanical design from one office and coordinated in BIM is the foundation of uptime.

A few minutes of downtime in a data center means lost data, stopped services and damaged trust. That is why data center projects require a very different discipline from the MEP design of an ordinary building. In this article we summarise what Sönmez Mühendislik has learned from more than 30 data center projects in Türkiye and abroad.

First, the target: which Tier level?

The internationally recognised Tier I–IV classification defines how well a facility keeps running during maintenance and failures. Fixing the right level at the start prevents expensive redesign later.

Redundancy: N, N+1 and 2N

TopologyMeaningResult
NMinimum equipment to carry the loadNo redundancy
N+1One spare unit on top of the needOperation continues through one failure or maintenance
2NA fully independent second copy of the systemHighest availability, highest cost

Generators, UPS systems, chillers and distribution boards must follow consistent decisions; one weak link lowers the level of the whole chain.

TargetTier levelPowerMV, transformer, UPSCoolingCapacity, PUECoordinationBIM, LOD 400CommissioningIntegrated tests
Figure 1 — Main steps of a data center project.

Power infrastructure

The power chain from the medium-voltage supply down to the rack is designed together with transformers, generators, UPS, batteries and distribution. Studies such as protection selectivity, earthing and harmonic analysis are invisible but decisive parts of uptime.

Cooling and energy efficiency

Cooling is a major part of operating cost. Hot/cold aisle layout, precision air conditioning, free cooling and liquid cooling for high-density racks determine the facility's energy efficiency (PUE).

Multi-discipline coordination and BIM

Cable trays, chilled water pipes, fire suppression lines and structural members meet in tight spaces. LOD 400 modelling in Revit and clash detection in Navisworks let us resolve this complexity before it reaches the site.

See our Services page for details of Sönmez Mühendislik's services, and our Blog for more technical articles.

Frequently asked questions

Click a question to see the answer.

Turkcell Data Center
ScopeWhich disciplines does a data center project cover?
Structural, electrical, mechanical, fire detection and suppression, low-current and automation systems. Designing them together is critical for uptime.
RedundancyWhat is the difference between N+1 and 2N?
N+1 adds one spare unit to what is needed; 2N provides a fully independent second copy of the system.
ConversionCan an existing building be converted into a data center?
Often yes, but floor loads, storey height and power/cooling capacity must first be verified by engineering analysis.
Turkcell Data Center
ExperienceHow many data center projects have you delivered?
Sönmez Mühendislik has provided engineering services on more than 30 data center projects in Türkiye and abroad.

Talk to us about your data center project.

Since 1995, Sönmez Mühendislik has delivered structural, electrical, mechanical and BIM projects in Türkiye and abroad, and is one of Türkiye's long-established engineering offices. With more than 80 specialists we provide engineering design, technical consultancy and project management.